Request for Quotes (RFQ) for the Supply of Service- Construction of New, and Renovation of Existing Structures for the Purpose of CFS/Safe Space at Ekklesiyar Yan’uwa a Nigeria (EYN PROJECT)

EYN Projects respects and believes in the infinite worth of every individual. We demonstrate this belief through our development and humanitarian services to affected communities, equal employment opportunities, building and strengthening staff’s skills, and ensuring qualitative and effective service delivery. EYN Projects does not discriminate based on gender, ethnicity, or religion in our recruitment exercise nor in our humanitarian and development work.

Experience2 years
Location Borno

EYN Projects in Partnership with Save the Children on GMMK ENRICH Project, implementing in Kaga Mobbar, Magumeri and Gubio LGAs,  with its United States Department of States Donor. This activity is targeted towards rehabilitating and Constructing structures for the Purpose of  Child friendly Space/Safe Space

 REQUEST FOR QUOTES (RFQ) FOR THE SUPPLY OF SERVICE- CONSTRUCTION OF NEW, AND RENOVATION OF EXISTING STRUCTURES FOR THE PURPOSE OF CFS/SAFE SPACE

 “RFQ N0:  EYNPN/ENRICH/GMMK/BORNO/OCT/2025/0579 “CONSTRUCTION AND RENOVATION”

CLOSING DATE: 6th November 2025, 5:00 PM

LOCATION: NIGERIA, BORNO STATE, GUBIO, MAGUMERI, MOBBAR, AND KAGA LOCAL GOVERNMENT AREAS

                                           ITEM / DISCRIPTION              UNIT    QUANTITY
Construction of new structures for th Purpose of CFS/Safe Space at Gubio LGA as indicated on the attached BoQEach1
Construction of new structures for th Purpose of CFS/Safe Space at Magumeri LGA as indicated on the attached BoQEach1 
Construction of new structures for th Purpose of CFS/Safe Space at Mobbar LGA as indicated on the attached BoQEach1
 Renovation of existing structures for the Purpose of CFS/Safe Space at Gubio LGA as indicated on the attached BoQEach1
    

To be considered, bidders should submit a complete quotation not later than the closing date and time indicated above. Bidders should ensure that the quotation is well written in English, easy to read, follows the instructions provided, and contains only requested information.

QUESTION: Any questions should be submitted in writing and emailed to [email protected] o later than two days after the issue date of this RFQ. No questions will be entertained if they are received by means other than the specified email address, and any communications to alternate e-mail addresses will result in the disqualification of the bidder.  The solicitation number (listed above) should be stated in the subject line. Answers will be compiled and distributed within 1 day from the closing date of questions

The Bidder is required to include details of three business references; this should include the name, company, and relationship to the bidder, email address, and / or phone number for each reference.

EYN Projects reserves the right to visit the place of business of a prospective supplier to verify that it is a legal business entity and has the necessary organizational and management competence to fulfill the necessary responsibilities.

  • All Bidders must provide proof of registration and tax. Attach CAC certificate, TIN Certificate and updated Tax Clearance Certificate when sending quotation.
  • All transportation and handling charges if any should be incorporated into vendor’s quoted unit price.

DISCLAIMER: – Brand Names: Specific brands and / or models indicated—while often preferred—are for description only.  An equivalent substitute, as determined by the specifications, will be acceptable.

The EYN projects estimates that the Construction and renovation Services will be completed within a period of 10 days. The selected bidder(s) should have the capacity of the Services needed by EYN projects within the aforementioned timeframe. The consumption range provided is an estimate, and EYN projects reserves the right to consume above or below this range, or to order partial Items, and the selected bidder(s) shall deliver accordingly. The selected bidder(s) must deliver the Service according to the provided timeline. EYN and its Donors reserve the right to have access to vendor/Company details of Procurement related documents in case of any misconduct.

TENDER REQUIREMENTS:  – 

To ensure that best value is obtained the following would be considered;

  1. Evidence of Vendor’s registration with CAC, Tax Identification number and updated Tax Clerance (Certificates) 
  2. Acceptable quotation validity period
  3. Availability of items
  4. Delivery within specified time
  5. Proof of experience
  6. three business references; this should include the name, company, and relationship to the bidder, email address, and / or phone number for each reference.
  7. Quotation is applicable to 2% withholding tax and 1% Stamp duty.

EVALUATION CRITERIA: BEST VALUE (Technical Specification 40%, Delivery Time 30%, Price reasonableness 30%): – Only quotations that meet the requirement above would be selected for evaluation. Please note that if there are significant deficiencies regarding responsiveness to the requirements of this RFQ, an offer may be deemed “non-responsive” and thereby disqualified from consideration. EYN Projects reserves the right to waive immaterial deficiencies at its discretion                                                                                                                              

       
BOQ for the construction of Child Friendly Space (CFS) at Magumeri, Mobbar and Gubio
S/N DESCRIPTIONUnitQTY Unit Price (₦)  Amount   NGN Amount USD
 Preliminaries
1Mobilization/Demobilization : Initial Mobilization and final demobilization of equipment, labour and materials to and from sitesum1   
 Total of Section A   
 Excavation and Earth Work
2Site clearance : Clear site of shrubs, grasses undergrowth and other unwanted materials from the surroundingsum1   
3Excavate trenches for wall foundations commencing from reduced level not exceeding 0.9m : Size of CFS main structure: 13m x 8.3m.Perimeter 40m (40*0.9*0.69)m³27.945   
4Levelling bottom of excavation : Level and compact bottom of excavation to receive concrete also rate include treatment of the foundation with anti termite as approved by the Engr.m224.84   
5Backfilling : Filling to excavation with selected materials from excavation; Compact to edges of facility block and dispose surplose off site after blockworkm324.84   
 Total of Section B  
 Concrete Structure
6Blinding : Cast 50mm blinding under blockwork with weak concrete of ratio 1:3:6m33.105   
7full length High tensile bar (BS4449) for footings, column, lintel and head course : Y12 – High yield reinforcement bar to be cut, bend and fix for footings (at 200c/c) and column starters as shown in drawingPcs40   
8full length High tensile bar (BS4449) for beams : Y12 – High yield reinforcement bar to be cut, bend and fix for resisting compression and tension in beams as shown in drawing
to be cut, bend and fix for stirrups (at 200c/c) 
Pcs20   
9Concrete for footings, columns, lintel and Head course : Cast plain M15 grade concrete (1:2:4); developing minimum 15N/mm2 working strength after 28 days of curing for both footings and columnsm315.525   
10Formwork for Beam : Sawn formwork to cover sides of beam, the beam is placed at the top of last coach of block to receive slab, superstructure and user load m210   
11Providing & laying Sandcrete block for structures using  cement mortar 1:4 (1 Cement, 4 Sand)Provide Blocks, Hollow  Sandceret blocks (Machine mould with mortar, 225x225x450mm) 9″. (Add 5% for damages)m2182.32   
12Blockwork for steps and ramps : Laying of sancrete blockwork (230x450mm) ; laid stretcher bond on cement and sand mortar (1:3)  this include cost for rendering and finishing m27   
13Total of Section C  
14Superstructure
15King post treated Wood hard  (Obeche or equivalent) 2″x6″x11′ for super structure : Supply, cut and nail full gauge this wood Pcs40   
16Botton chord (Beam) treated Wood hard  (Obeche or equivalent) 2″x6″x11′ for super structure : Supply, cut and nail full gauge this wood Pcs120   
17Top chord (Beam) treated Wood hard  (Obeche or equivalent) 2″x6″x11′ for super structure : Supply, cut and nail full gauge this wood Pcs170   
18Purlins treated Wood hard (Obeche or equivalent) 2″x3″x11′ for super structure : Supply, cut and nail full gauge 2×3″ wood Pcs160   
20Provide and fix of noggings (50X50mm)  treated Wood hard  (Obeche or equivalent)Pcs180   
21Provide and fix of ceiling boards (brazil)  with painting of the Ceilling of 2.4m x 1.2m  to covering the 13mx8.2m struture including battens and painting of the Ceillingm²106.6   
22Long span aluminium roof 0.55mm thick with all required accessoriesm3140   
23Provide and install windows with accessories : Windows ironmongery (locks, hinges) using 2mm chaquered plate and pure black iron  1.2×1.2mPcs8   
24Doors with accessories door ironmongery (locks, hinges) – allowance using 2mm chaquered plate and pure black iron 0.9×2.1mPcs4   
25Fascia board 12 ft × 2 ft : Supply and install Pcs13   
 Total of Section D  
 Finishes
26Allow for Cast plain M15 grade concrete (1:2:4); developing minimum 15N/mm2 working strength after 28 days of curing for floor with thickness 100mm and Internal  Screed internal floor with concrete of gauge 25mm (1″) m39.1   
27Rendering & Dressing : Rendering and dressing of concrete structure   external and internal sand mortar (1:3)m²262.88   
28Allow paiting  of internal & external wall using approved muti -color satin & gloss paint as directed by SCI and EYN Engineer . See attached samplem²262.88   
29Allow for provision of branding and visibility of the CFS, including preparing   surface with 2 coats of paints, engraving of words and logos as shown on the branding template (1 mounted on ground, Metallic plate vsilibilty (Front and Back): Message to be provided by SCI and EYN EngineerPcs1   
 SUBTOTAL     
TOTAL ESTIMATED COST

s

        
Child Friendly Space (CFS) Renovation at Kaga LGA
S/nDescriptionUnitQuantity Unit Rate (NGN)  Amount (NGN) Amount USDRemarks
1Mobilization ,Site clearance and removal of existing damaged roofing & timber (dispose)LS1   Remove and dispose damaged materials
2Supply & install rafters/tie beam (structural framing) using treated hardwood timber 50×150mm for a 13m × 7m roof area (~91 sqm)pcs100   Treat timber against termites
3Supply & install  struct using treated hardwood timber 50x100m struct pcs70    
4Allow for repair and replacement of bad noggings (50X50mm)  treated Wood hard  (Obeche or equivalent) for main struturepcs100   Treat timber against termites
5Install entire ceiling (brazil) of 13mx7m of the main struture including battens and  painting of the Ceillingm²             91.00     
6Allow for repair and replacement of bad noggings (50X50mm)  treated Wood hard  (Obeche or equivalent) for store (storage room)  and a store (storage room).pcs16    
7Install entire ceiling (brazil) of 2mx7m of the store struture including battens and  painting of the Ceillingm²             14.00     
8Providing & laying Sandcrete block to create of partition walls from counselling room and a store (storage room).m²35.26    
9Rendering & Dressing : Rendering and dressing of concrete structure   external and internal sand mortar (1:3) m² 50.84    
10Nails, screws, and roofing fasteners (Nail, common wire nail, round head, 3″) kg 20   Estimate
11Nails, screws, and roofing fasteners (Nail, common wire nail, round head, 1 1/2″)kg10   Estimate
12Supply & install 1 no. steel door for store  and counselling room using 3mm chaquered plate and pure black materials (including frame & lock) (0.95n by 2m)nos2   Store currently has no door
13Repair 4 window shutters (including hinges & frames) 1.2×1.2m nos                5.00    Windows hard to close; need repair/replace
14Doors with accessories door ironmongery (locks, hinges) – allowance using 2mm chaquered plate and pure black iron 0.9×2.1m Pcs                1.00    Minor cracks observed
15Allow for hacking of all cracks (knitting of crack using yarn and Y6 bars, replastering and fine finishing)  sum                1.00    Finish
16Allow for floor concrete and screeding estimated  sand mortar (1:3) sum                1.00    Includes posts and fixing
17Allow for Chainlink fence repair/replacement (17 linear metres) Foreign corrugated GI wire mesh (6mm thick with 2″ spacing, size 1.2m x 3.6m)m17    
18Supply and install Square Pipe (2″x2″, 3mm, 6m)pcs10   Gate currently open/insecure
19Supply & install main entrance gate using 3mm chaquered plate and pure black irons (steel) 3.5×2.3 mnos1    
20Allow paiting  of internal & external wall using approved muti -color satin & gloss paint as directed by SCI and EYN Engineers . See attached samplem²262.88    
21Allow for provision of branding and visibility of the CFS, including preparing   surface with 2 coats of paints, engraving of words and logos as shown on the branding template (1 mounted on ground, Metallic plate vsilibilty (Front and Back): Message to be provided by SCI and EYN Engineernos1    
 SUBTOTAL      
 TOTAL ESTIMATED COST   

Method of Application

Quotations must be submitted via email to: [email protected] with the subject line: EYNPN/ENRICH/GMMK/BORNO/OCT/2025/0579 “CONSTRUCTION AND RENOVATION””.

Share this job:
Facebook Twitter LinkedIn Email Print